Aware

Aware for Supply Chain

Turn government action into supply-chain advantage

Aware connects government action to your supply chain, quantifies the financial and continuity consequence, tests executable responses against inventory, qualification, capacity, timing, and contract constraints, and gives your team the Next Move. The goal is not only resilience. It is turning faster action into business advantage.

Exposure Mapr-magnet-bis-01

Value chain · what this action touches

Highlighted entities are the ones a consequence reaches, coloured by the order that reaches them first.

Inputs & Suppliers

  • Nd-Pr sintered magnets
  • Magnet route JP-02
  • Rotor laminations
  • Power electronics

Manufacturing & Operations

  • Plant 2 — drive-unit assembly
  • Traction-motor line
  • Plant 4 — inverter
  • Qualification & PPAP

Customers & Markets

  • Programme A — EV drive unit
  • Programme B — commercial
  • Aftermarket
  1. Government action. Licence requirement extended to Nd-Pr sintered magnets and precursor alloysBIS / U.S. Dept of Commerce · 91 FR 48213
  2. 1st order · Direct. Magnet allocation to Plant 2 falls 38%1,180 t/yr contracted → 732 t/yr licensedOwned by Supply Chain
  3. 1st order · Direct. Landed cost on the remaining qualified route +14%+$1.40/kg on 732 tOwned by Sourcing
  4. 2nd order · Ripple. Traction-motor line loses 11 days of capacity732 t supports 89 of 100 build daysOwned by Operations
  5. 2nd order · Ripple. Two customer programmes move to allocation delivery41% of drive-unit volume moves to allocationOwned by Sales
  6. 3rd order · Systemic. ~$41M of FY revenue at risk11 days × $3.7M/day of drive-unit revenueOwned by Finance
  7. 3rd order · Systemic. Segment operating margin −60 bpsSame fixed base over 89 days instead of 100Owned by Finance

The path the recommended move acts onConsequences it does not address

The gold path is what the recommendation acts on: B · Qualify the Japanese secondary magnet route. It closes the allocation gap and the 11-day capacity loss behind it. The two grey branches — landed cost and the margin effect — it does not touch, and that is the argument worth having.

Illustrative worked example. Route identities are coded and quantities are modelled from public data — at pilot both are replaced by your own systems.

From exposure to executable response

See what is exposed, quantify the financial and continuity consequence, then move before the response window closes.

  1. 01

    Trace

    Find where exposure sits

    Follow the action through direct suppliers, upstream dependencies, materials, products, facilities, contracts, and markets.

  2. 02

    Quantify

    Measure cost, revenue, margin, and continuity

    Estimate direct cost, revenue at risk, margin effect, inventory coverage, continuity, and timing while keeping confirmed facts, assumptions, and missing information distinct.

  3. 03

    Compare

    Test executable responses

    Check approved suppliers, qualification, capacity, contracts, technical constraints, inventory, lead time, and earliest delivery.

  4. 04

    Act + measure

    Make the Next Move operational

    Assign the owner, start-by date, approvals, dependencies, consequence of delay, and projected versus realized value.

  5. Outcome

    Turn response speed into competitive advantage

    Move while alternate capacity, qualification windows, supplier options, and customer commitments are still available.

Worked example

One government action, followed through the supply chain

Exposure chain

Government action to revenue

  1. Government Action
  2. Supplier
  3. Material
  4. Product
  5. Facility
  6. Revenue

Show how the same action reaches cost, continuity, customer delivery, and timing.

Response chain

Options that survive reality

  1. Current Suppliers
  2. Qualification
  3. Capacity
  4. Timing
  5. Contract
  6. Next Move

The recommended response makes the earliest start-by date and consequence of waiting explicit.

Next Move4 options · 1 recommended

What doing nothing costsEleven build days of traction-motor capacity and ~$41M of FY revenue, against a licence decision window that closes 12 Nov.

Every option, on the things that decide it

Response options for BIS interim final rule — export licensing on Nd-Pr sintered magnets, compared on year-one cash, residual exposure, time to effect, approvals outside our control and effect on availability.

Response options compared on year-one cash, residual exposure, time to effect, approvals outside our control and effect on availability.
OptionCash, year oneExposure left afterHow fast it worksApprovals we don't controlEffect on availability
AHold allocation and monitor the licence docketKeep the current route, file comments before the window closes, and re-plan when the first licence decisions publish.$0M$41Mnot modelled0No change — the 11-day gap stands.
BQualify the Japanese secondary magnet routeRecommendedRun the already-scoped qualification on route JP-02 — site audit, line trial and customer PPAP on both drive-unit programmes.$31M$7M9–14 wk2Closes the gap to 3 days from Q3; full cover from Q4.
CPre-build magnet inventory before the licence takes effectDraw forward the volume that clears under the current licence and hold it against the Q3 build plan.$9M$25M3–5 wk0Buys 6 weeks of cover, then the gap returns unchanged.
DRedesign to the ferrite-assist motor variantMove both drive-unit programmes onto the ferrite-assist rotor already validated on the commercial platform.$28M$2M38–52 wk3Removes the dependency from FY28 — no effect on this year's gap.

We recommend B · Qualify the Japanese secondary magnet route

B is the only option that changes the allocation position before the licence window closes on 12 Nov. D removes the dependency outright and carries the better long-run position, but its first qualified part lands in FY28 — three quarters after the capacity gap it is meant to close. Run D behind B, not instead of it.

What would change our answer: BIS issues the general licence for automotive end-use currently under consultation. If it publishes, the 38% allocation cut does not bind and C — a six-week pre-build — is sufficient on its own.

VP Supply Chain approves the qualification spend before the line trial books.Start by 24 Oct 2026Cost of waiting $3.7M per build day after 12 Nov

Illustrative worked example. Route identities are coded and quantities are modelled from public data — at pilot both are replaced by your own systems.

How it is delivered

Start in SaaS. Connect deeper supply-chain systems as value grows.

Begin with company context and structured data, then add supported procurement, ERP, planning, document, and data integrations where they improve the decision.

  • Procurement + ERP
  • Planning + inventory
  • Documents + supplier evidence
  • Action routing + reporting

Supply chain pricing

One Supply Chain subscription that scales with your deployment

The Supply Chain version keeps the same commercial structure as Platform, with a modest premium for deeper supplier, material, inventory, qualification, capacity, and continuity logic.

Indicative pricing. Final pricing is confirmed in writing before contracting. Supplier-discovery rights are scoped separately, as are custom and complex integrations — bespoke supplier or material mapping, unsupported systems, and custom workflow logic.

Aware for Supply Chain

1 company environment, up to 10 users, 1 standard supply-chain integration, and the full supply-chain optimized decision workflow

Annual billing$33,000 / yr

Monthly billing$3,163 / mo

Expansion items
ItemWhat it coversAnnual billingMonthly billing
Additional company environmentA separate company model or materially separate operating entity with its own supply-chain context and decision spaceA separate company model or materially separate operating entity with its own supply-chain context and decision space

+$6,600 / yr

+$633 / mo

Additional userEach active user beyond the 10 included seatsEach active user beyond the 10 included seats

+$660 / user / yr

+$63 / user / mo

Additional standard integrationOne supported procurement, ERP, planning, inventory, document, or data connector with normal mapping and maintenanceOne supported procurement, ERP, planning, inventory, document, or data connector with normal mapping and maintenance

+$3,300 / yr

+$316 / mo

Custom / complex integrationUnsupported systems, bespoke supplier/material mapping, custom workflow logic, or materially higher implementation effortUnsupported systems, bespoke supplier/material mapping, custom workflow logic, or materially higher implementation effortCustom
  • 14-day free trial
  • 10 users included
  • 1 company environment included
  • 1 standard integration included
  • Supplier discovery rights scoped separately

Start with 14 days on a real supply-chain decision

Test exposure, financial and continuity impact, constraints, options, and the Next Move before choosing annual or monthly billing.

Start 14-Day Free Trial

Turn an executable supply-chain response into business advantage

Trace the consequence, test the constraints, and make the Next Move before capacity, qualification, or customer windows close.